CISD Board Meeting Monitor Constituent summaries of Conroe ISD board meetings
← All Meetings
Unofficial summaries generated from public board meeting records. Not affiliated with or endorsed by Conroe Independent School District.

February 23, 2021 — Regular Meeting

Conroe Independent School District Board of Trustees — Regular Meeting

View interactive version →

Conroe ISD Board Meeting — 2021-02-23

Regular Meeting — Unofficial Notes

Based on auto-generated transcript. Not an official record.

Generated 2026-03-28 13:34 UTC


Unofficial Meeting Notes

Conroe Independent School District Board of Trustees — Regular Meeting

February 23, 2021

Note: These are unofficial notes based on an auto-generated transcript of the board meeting. They are intended to help the public understand what occurred but are not official minutes.


Opening


Awards & Recognition

A. 2021 TMEA All-State Musicians

B. Child Nutrition COVID-19 Response Recognition

- Lydia Powell — Conroe High School

- Tammy Long — McCullough Junior High

- Nuri Posey — Bush Elementary

- Juanita Sydell — Caney Creek High School (unable to attend)


Citizen Participation


Consent Agenda (Item 4)


Administration (Item 5)

A. Resolution Requesting COVID-19 Vaccine Phase 1C for Teachers and School District Employees

B. Hope Elementary School Mascot and Colors (Informational)

C. Teacher Incentive Allotment (TIA) Program Development (Informational)

- Recognized: $3,000–$9,000

- Exemplary: $6,000–$18,000

- Master: $12,000–$32,000

- Board approval recommendation targeted for March 2021

- Application submission to the state by April 15, 2021

- Data gathering in 2021–2022

- Compensation begins Spring 2023


Construction & Facilities (Item 6)

A. Conroe High School Master Plan Phase 2 — Guaranteed Maximum Price (GMP)

B. New Elementary in Conroe HS Feeder Zone (Flex 21) — GMP

C. Construction Manager at Risk for Campus Renovations 2022

D. Capital Improvement Update (Informational)

Mr. Foster provided project-by-project updates:

| Project | Status | Target Completion |

|---|---|---|

| Hope Elementary | ~90% exterior complete; interior showing red/black color scheme | August 2021 |

| Runyan Elementary (addition/renovation) | Complete — all spaces occupied and in use | Done |

| York Junior High (addition to 2,000 capacity) | Structure nearing dry-in; interior work underway | August 2021 |

| College Park HS (addition to reduce portables) | Nearing dry-in; windows/masonry in progress | August 2021 |

| The Woodlands HS (addition to reduce portables) | Roofing near complete; exterior masonry underway | August 2021 |

| Armstrong Elementary (kitchen renovation/addition) | Underground utilities in; foundations next | August 2021 |

| Creighton Elementary (major overhaul — roof, HVAC, sprinkler, ADA, security) | Roof replacement underway; fire tank foundation in progress | August 2022 (two summers) |

| New Junior High, Caney Creek feeder zone (62-acre site) | Site cleared; building pad/foundation work underway; large detention pond under construction | August 2023 |

| Conroe HS Master Plan | Road work/bus loop construction underway on north side; JV bleachers dismantled and retained for reuse | 2025 |

| Teacher Training Center (Woodforest Stadium) | Parking/driveway cut; underground utility relocation; building pad excavation | ~12 months out |


Purchasing (Item 7)

A. Furniture for Hope Elementary (RFP 20-11-01)

B. Internal Connections Campus Refresh / E-Rate (CSP 20-12-01)

C. Musical Instruments and Supplies (RFP 20-12-06)

D. Financial Reports (Informational)

- General Fund cash: $392.1 million (majority in state pools at $303.7M)

- Debt Service: $105.2M in cash; first debt payment of $73M processed before the storm

- General Fund revenue YTD: $405 million

- 2019 Bond: $153.9M encumbered/expended; $482.5M remaining

- Self-Funded Insurance: Positive YTD by $233,500; wellness center averaging 348 visits/month

- Investment portfolio par value: $815.2 million; combined yield of 0.223%

- Interest rates beginning to tick upward; tax collections arriving.


Executive Session


Action from Executive Session (Item 10)

A. Termination of Probationary Contract — Erin Baker

B. Local Policy Manual Update 116 (Informational)

- Legal policies (restatements of law) were updated based on administrative regulations from the last legislative session, effective January 2021.

- BQA (Local) — District-level planning process: cleanup to align policy with existing practice.

- EIE/EIU (Local) — Grading policy: expanded language for more flexibility in grading/reporting at lower grade levels.


Adjournment


Summary of Votes

| Item | Result |

|---|---|

| Consent Agenda | Passed unanimously |

| COVID-19 Vaccine Resolution (Phase 1C for teachers) | Passed unanimously |

| Conroe HS Phase 2 GMP ($145.0M) | Passed unanimously |

| New Elementary (Flex 21) GMP ($29.6M) | Passed unanimously |

| CMAR Selection — GTT Contractors (Campus Renovations 2022) | Passed unanimously |

| Furniture for Hope Elementary ($650K) | Passed unanimously |

| E-Rate Campus Tech Refresh ($2.4M) | Passed unanimously |

| Musical Instruments & Supplies ($700K) | Passed unanimously |

| Termination of Erin Baker's Probationary Contract | Passed (one abstention) |